HOCHTIEF ·
·

Katowice

  

(©HOCHTIEF Polska)

Time of construction: 10.2013-03.2014
Usable area: 560 square metres
Cubage: 3,360 cubic metres
Contractor: Consortium of HOCHTIEF Polska Branch in Krakow (leader)
Investor: Gornoslaskie Towarzystwo Lotnicze S.A.

Characterisation: Reconstruction of the Terminal A included the demolition of the existing luggage room / EDS in the departure part of the terminal and the construction of a new facility as well as reconstruction of the existing building and the BHS system.